The National Energy Administration defines the matters related to the development and construction of wind power and photovoltaic power generation in 2021

Create_time:2022-01-13 Views:107

On May 20, the National Energy Administration recently issued the notice on matters related to the development and construction of wind power and photovoltaic power generation in 2021: the wind power and photovoltaic power generation projects to be connected to the grid in 2021 are mainly stock projects, including wind power projects approved before the end of 2020 and within the validity period of approval, parity wind power photovoltaic projects and bidding photovoltaic projects in 2019 and 2020, The scale is about 90 million KW.



Considering the construction period of the project, in order to ensure the grid connection of wind power and photovoltaic power generation projects in 2022 as scheduled and ensure the completion of the responsibility weight of renewable energy power consumption in 2022, it is necessary to reserve the projects to be grid connected in 2022 this year.